As of Apr 1 2023 it is 10 weeks
NOW 4-6 Weeks
Just so you know it is not just us – but all plants in the world have the same issues.
Here are stories by magazines on this issue
Here’s a UK News Story
and more
and TV stations
and USA Magazine
and another USA Mag
Three crazy things happened
1) plant had a corvid outbreak (a guy died) closed for two weeks
2) Apollo Plant that make 90% of all parts for making records burnt down
3) Record sales are up 25% and Walmart is ordering
because records are selling — the record store are empty — they then call the record labels — they are out — the labels call the plant. To added to this Walmart has discovered records. So they call Warner and ask for 100,000 Fleetwood Mac Records. Warner calls the plant and places a 2,000,00 dollars order. The plant says we promised one of Paul’s customer that we would get his records done in 2 weeks. Warner says do u want the million dollars or not. U know what happens. So things are delayed.